Storage Tank Design – Calculations, 3D Model and Fabrication Drawings
For storage tank design we start from the product, capacity and site conditions and select the right code before any plate is sized. The same approach covers a small diesel day tank and a large field-erected crude tank.
We design new storage tanks and check existing ones for water, crude oil, diesel, chemicals and fire water. Deliverables include shell, bottom and roof calculations, wind and seismic checks, nozzle orientation, GA and fabrication drawings, and API 653 repair calculations.
Also searched as: water tank, oil tank, diesel tank, fire water tank.
Last updated:
Request Engineering Support
Typical response within 24 hours · Confidentiality assured
SLETEC portfolio
Project Evidence — API 650 Roof Access, Hydrostatic & Safety Verification
Selected engineering evidence from SLETEC projects. Client names and identifiers are withheld for confidentiality.
Scope
Roof access, temporary works, anchors, hydrostatic shell checks
Codes
API 650 · AISC 360 · project criteria
Deliverables
Verification reports with reactions and acceptance checks
What we deliver
Send us your data sheet, sketch or old drawing on WhatsApp (+966 55 545 8298) or email (enquiry@sletec.com) for a fixed-price quote, usually within 24 hours.
Choosing the code: water tank design, fuel tank design and more
The stored product and the tank shape decide the governing code. Getting this right at the start avoids redesign when the inspector or client reviews the package.
| Code | What it governs |
|---|---|
| API 650 | Welded vertical tanks for oil, fuel, chemicals and fire water at near-atmospheric pressure |
| AWWA D100 | Welded steel tanks for potable and process water storage |
| UL-142 | Shop-built horizontal and vertical steel tanks for flammable and combustible liquids |
| API 620 | Large welded tanks at low internal pressure above the API 650 limit |
| API 2000 | Normal and emergency venting of atmospheric and low-pressure tanks |
Inputs that change the design
Specific gravity, design temperature and corrosion allowance set the shell course thicknesses. Wind speed sets the need for a top or intermediate wind girder, and the seismic zone decides whether anchors are needed to resist overturning. Soil settlement data from the geotechnical report affects the bottom slope and the foundation choice.
What the tank fabrication drawings include
Drawings show shell plate layout with weld seams staggered as the code requires, bottom and annular plate layout, roof framing, nozzle and manway details, and stair and platform arrangement. Our API 650 storage tank project and tank FEA verification project show typical outputs.
Problems we see on tanks in service
Owners usually call us when something has changed: a new product with a higher specific gravity, a heater coil that raises the temperature, or a new nozzle cut into a shell course. Other common triggers are shell bulging near the bottom course, bottom plate corrosion found during an out-of-service inspection, and vents that were never sized for the current pumping rate. Each is assessed against API 653 with a clear statement of what can stay and what must be repaired. Our guide to tank change of service for a heavier liquid explains the checks we run before a new product goes in.
Related engineering topics
API 650 tank design, API 653 tank repair, API 650 tank design project and API 650 tank design Saudi Arabia.
Frequently Asked Questions
Can you design a storage tank for our project?
Yes. We prepare calculations and drawings to API 650 / API 653 and your project specification.
Do you take small jobs?
Yes. Single drawings, one calculation or a check of an existing design are welcome.
Which countries do you serve?
Saudi Arabia, UAE, Qatar, Oman, Kuwait, Bahrain and worldwide.
Related pages
Serving all GCC countries
Send your sketch, photo or PDF today