Engineering guide
API 650 Storage Tank Design in Saudi Arabia: Codes, Loads and Deliverables
What owners, EPC contractors and fabricators need to define before an API 650 tank is designed for a Saudi project — and what a complete design package should contain.
By SLETEC Engineering · Updated 2026-11-06 · 6 min read
Which code applies: API 650, API 620 or API 653?
API 650 covers welded steel tanks for oil storage at internal pressures approximating atmospheric pressure, and up to 2.5 psig (about 18 kPa) under its Annex F, with metal temperatures up to 260 °C under its high-temperature annex. It is the standard for most atmospheric crude, product, water and chemical tanks.
API 620 applies to large low-pressure tanks above the API 650 pressure range, up to 15 psig. API 653 governs inspection, repair, alteration and reconstruction of tanks already in service — so a change of service, a new nozzle in an existing shell or a bottom replacement is an API 653 job, even if the tank was built to API 650.
On Saudi projects the code is almost always combined with a client specification. Saudi Aramco projects add the relevant SAES and SAMSS documents; SABIC, Ma'aden and other owners have their own requirements. These must be identified at the start, because they often go beyond the code — for example on minimum thicknesses, corrosion allowance, nozzle reinforcement or foundation details.
Design data to fix before design starts
| Item | Why it matters |
|---|---|
| Diameter, height, design liquid level | Sets shell course thicknesses and the 1-foot or variable-design-point method |
| Specific gravity of stored liquid and hydrotest water | Shell thickness is the greater of the design (product) and hydrotest cases |
| Design pressure and vacuum | Affects roof design, venting (API 2000) and anchorage |
| Design metal temperature, maximum temperature | Material selection, toughness and allowable stress reduction |
| Corrosion allowance by component | Added to shell, bottom, roof and structure thicknesses |
| Wind speed and exposure | Shell stability, wind girders, overturning and anchorage |
| Seismic parameters | Annex E: sloshing wave height, overturning, sliding, anchorage and freeboard |
| Roof type | Self-supporting dome or cone, supported cone, or floating roof — each changes structure and access design |
| Nozzle schedule and external loads | Nozzle reinforcement and shell stresses from connected piping |
| Soil report | Foundation type (ringwall, slab or compacted pad) and settlement limits |
Loads that often govern in Saudi Arabia
Coastal sites in the Eastern Province and on the Red Sea coast combine high temperatures, wind and corrosive atmospheres. Typical governing checks are:
- Wind stability of tall, thin upper shell courses, which drives top and intermediate wind girders.
- Seismic overturning and sloshing where the site hazard requires API 650 Annex E checks, and the resulting freeboard for roof clearance.
- Uplift and anchorage from internal pressure combined with wind or seismic loads.
- Roof live loads and access — platforms, handrails, maintenance loads and occasional scaffold loads through roof manholes.
- Nozzle loads from thermal expansion of connected piping, especially on lower shell courses.
When FEA adds value
The code formulas cover the standard cases. FEA is worth the effort when something is unusual: a new opening in an old shell, a support or platform loading the roof, local settlement, a heavier liquid than the original design, or a repair that changes stiffness.
Two SLETEC examples show the type of answer FEA gives:
- Heavier liquid in an existing tank (Ref. 79). An existing Ø6,096 mm tank with a 5.3 mm shell had to store a 1.83 SG fluid. Static-structural FEA under the hydrostatic gradient established a safe filling height of 4,450 mm at a maximum shell stress of 48.02 MPa — a clear operating limit for the owner.
- Scaffold access through the roof (Ref. 77). FEA of the dome roof under gravity, wind and scaffold interface loads gave a maximum vertical deformation of +0.51 mm and a total support reaction of about 4.90 × 10⁴ N, and access was approved within serviceability limits.
What a complete tank design package contains
- Design basis with codes, client specifications, loads and assumptions.
- Design calculations: shell, bottom and annular plates, roof and roof structure, wind girders, seismic, anchorage, nozzle reinforcement and venting.
- General arrangement drawing with nozzle orientation and schedule.
- Detail and fabrication drawings: shell development, bottom and roof plate layouts, nozzles, manways, stairways, platforms and handrails.
- Foundation loads and, where included, foundation design drawings.
- Material take-off and bill of materials.
- FEA reports where the scope requires them, with acceptance criteria stated.
Common mistakes that cause rework
- Design basis agreed too late. Starting calculations before the specific gravity, corrosion allowance and seismic parameters are frozen almost always means recalculating shell courses.
- Client specification read after the code. Owner standards frequently set minimum thicknesses, nozzle details or bottom slopes that differ from API 650 defaults. They should be in the design basis from day one.
- Nozzle loads ignored. Piping designers and tank designers need to exchange allowable and actual nozzle loads early; late changes can force reinforcement or shell thickening.
- Access added without roof checks. New platforms, handrails or maintenance access on an existing roof need a structural check — the roof was not necessarily designed for them.
- Foundation and tank designed separately. Settlement limits, anchor bolt positions and ringwall dimensions must match between the two packages.
Typical design sequence and timeline
| Stage | Output |
|---|---|
| 1. Input review | Query log listing missing or conflicting data |
| 2. Design basis | Codes, specifications, loads, materials and acceptance criteria agreed with the client |
| 3. Calculations | Shell, bottom, roof, wind, seismic, anchorage, nozzles and venting |
| 4. Drawings | GA, nozzle orientation, plate layouts and details, issued for review (IFR) |
| 5. Independent check | Recorded check by an engineer who did not prepare the work |
| 6. Client review and comment closure | Comment-response sheet; revised issue for approval (IFA) and for construction (IFC) |
Duration depends on tank size, the number of nozzles and accessories, and the client review period. A realistic offer lists the inputs required and the review periods, not only a delivery date.
What to send for a quotation
To price a tank design accurately we need the data sheet or the items in the table above, any client specifications, the soil report if foundations are included, and the deliverable list and schedule. For an existing tank, add the original drawings, the latest inspection report and photographs. Send them to enquiry@sletec.com or see our API 650 tank design service.
Frequently asked questions
- What is the difference between API 650 and API 653?
- API 650 covers the design and construction of new welded steel storage tanks. API 653 covers inspection, repair, alteration and reconstruction of tanks already in service.
- Does API 650 apply to pressurised tanks?
- API 650 covers tanks at near-atmospheric pressure and, under Annex F, up to 2.5 psig (about 18 kPa). Higher low-pressure tanks, up to 15 psig, are designed to API 620.
- Do Saudi Aramco projects use only API 650?
- No. Saudi Aramco projects combine API 650 with the applicable Saudi Aramco Engineering Standards (SAES) and Materials System Specifications (SAMSS), which often add requirements beyond the code.
- When is FEA needed for a storage tank?
- When the case is outside the standard code formulas — for example a heavier liquid in an existing tank, new openings or attachments, roof-supported loads, local settlement or repairs that change stiffness.
Start a project
Send your scope, drawings, codes and schedule to enquiry@sletec.com or WhatsApp +966 55 545 8298. An engineer usually replies within 24 hours.
Discuss your project with an engineer
Send drawings, datasheets or a short scope – an engineer replies with scope, schedule and price, usually within 24 hours.