Heat Exchanger Rerating and Re-Assessment of Existing Units

SLETEC provides heat exchanger rerating for existing shell-and-tube units, checking whether a unit can take a new pressure, temperature, duty or fluid both thermally and mechanically. We work from the original datasheet, drawings and current inspection data, and issue a controlled calculation package that the owner's inspector can use to update the nameplate and records.

Last updated:

When an existing exchanger needs rerating

Most rerating requests start with a process change rather than a problem with the exchanger. A debottlenecking study raises throughput, a feed slate changes, or a spare unit from another service is proposed for reuse. In each case the question is the same: can the existing shell, channel, tubesheet and bundle accept the new conditions without replacement.

Rerating also follows inspection findings. If wall thinning has consumed part of the corrosion allowance, the owner may prefer to lower the design pressure or temperature rather than repair, and the unit must be recalculated at the reduced conditions with the measured thicknesses.

  • Higher design pressure or temperature on shell side, tube side or both
  • Change of service fluid, fouling factor or flow rate
  • Lower minimum design metal temperature (MDMT) for start-up or depressurisation cases
  • Reduced thickness after corrosion, requiring re-assessment at measured values
  • Reuse of a spare or relocated exchanger in a different duty

Thermal re-check of the existing bundle

The thermal re-check is a rating calculation, not a sizing one. The geometry is fixed: shell diameter, tube count, tube length, pitch, baffle cut and spacing, and pass arrangement come from the as-built drawings. We run the new process conditions through that geometry to find the achievable duty, the outlet temperatures and the overdesign margin against the required fouling resistance.

Pressure drop and flow-induced vibration are checked at the same time. Higher flow rates can push shell-side velocities past acceptable limits at the inlet and outlet baffle spaces, and a bundle that was quiet in its original service can become prone to vortex shedding or fluid-elastic instability. Where the margin is short, we look at practical changes such as a different number of tube passes, impingement protection or a modified inlet before recommending a new bundle.

Mechanical re-assessment to TEMA and the construction code

The mechanical check follows the code the exchanger was built to, usually ASME Section VIII Division 1, PD 5500 or EN 13445, together with the TEMA class (R, C or B) stated on the datasheet. Each pressure part is recalculated at the new conditions using the current corrosion allowance and, where available, measured thicknesses from the latest inspection report.

Tubesheets and expansion joints usually govern. A higher shell-side temperature changes the differential thermal expansion between shell and tubes in a fixed-tubesheet unit, which raises tubesheet and tube-to-tubesheet joint loads and may require an expansion bellows. Body flanges and girth flanges are checked for the new bolt load and gasket seating, and nozzles are checked for reinforcement and for the piping loads at the revised conditions.

Typical mechanical checks in a rerating package
ComponentWhat is checkedCommon outcome
Shell, channel and headsRequired thickness at new pressure and temperature with remaining corrosion allowanceUsually acceptable; governs if heavily corroded
TubesheetBending and shear for all load cases, including differential expansionOften the limiting component
Tubes and tube jointsInternal and external pressure, axial load and joint strengthMay limit fixed-tubesheet units
Flanges and boltingBolt load, flange stress and rigidity at new conditionsBolt material upgrade sometimes needed
NozzlesReinforcement and local stress from piping loadsPad or load reduction where short
Expansion jointStroke, stress and fatigue for revised thermal casesReplacement or new joint in some cases

Inputs we need from the owner

A rerating is only as good as the records behind it. We ask for the original manufacturer's data report or equivalent, the datasheet, general arrangement and detail drawings, material certificates where available, and the most recent thickness survey. The new process conditions should come from the process licensor or the owner's process engineer with the relevant cases identified.

When original drawings are missing, the geometry can be recovered by site measurement or reverse engineering of the existing unit. Material grades that cannot be confirmed from records are taken conservatively, and we state every such assumption in the design basis so that the inspector can see where the result depends on it.

Code requirements for rerating an in-service unit

For pressure equipment in service, rerating is governed by the owner's inspection code, typically API 510 for exchanger shells and channels in refineries and petrochemical plants. That code expects calculations by a competent engineer, a review of the inspection history, consideration of whether a new pressure test is required, and approval by the authorised inspector before the nameplate is changed.

SLETEC prepares the engineering part of that process. The decision to rerate, the pressure test if required and the nameplate stamping remain with the owner and the authorised inspector. Our package is written so that each of those people can follow the logic, with clear references to the code edition used and to the inspection data relied on.

Deliverables and checking

A typical rerating package contains a design basis, the thermal rating output with a summary of margins, the mechanical calculation for every pressure part, a list of limiting components, and recommendations where the unit does not pass as it stands. Where a modification is needed, such as a new expansion joint or upgraded bolting, we can add the fabrication drawings for it.

Every calculation goes through self-check, independent check and approval before issue, and the documents are numbered and revision-controlled. Our project references include shell-and-tube exchanger rerating to PD 5500, nozzle-load assessment to WRC 537 and static and fatigue assessments of existing exchangers.

Rerating or new design

Sometimes the honest answer is that the existing unit cannot be made to work economically. If the thermal margin is negative and the tubesheet is already at its limit, a new bundle or a new exchanger is usually the better route. In that case our heat exchanger design service covers thermal sizing and mechanical design of the replacement to TEMA and the owner's specification.

Frequently asked questions

Can a heat exchanger be rerated to a higher pressure?

Often it can, if the existing thicknesses, tubesheet, flanges and bolting pass the code calculation at the new pressure with the remaining corrosion allowance. A new hydrostatic test is usually considered for an increase in design pressure, and the owner's authorised inspector decides whether one is required. The nameplate is updated only after that approval.

What information is needed for a heat exchanger rerating?

The datasheet, manufacturer's drawings and data report, the latest thickness survey and the new process conditions are the core inputs. Material certificates and the original calculation help but are not always essential. Missing data is covered by site measurement or conservative assumptions stated in the design basis.

Which component usually limits a shell-and-tube exchanger rerating?

The tubesheet is the most common limit, especially in fixed-tubesheet units where differential thermal expansion between shell and tubes increases with temperature. Body flanges, bolting and expansion joints are the next most frequent limits. Cylindrical shells and channels usually have more margin.

Do you rerate exchangers built to PD 5500 or EN 13445?

Yes. We recalculate to the code the unit was built to, which may be ASME Section VIII, PD 5500 or EN 13445, together with the TEMA class on the datasheet. If the owner wants a different code applied, that is agreed and recorded in the design basis before the work starts.