As-Built Drawing & Final Record Dossier — Brownfield Project
This as-built dossier project closed out a brownfield revamp at a petrochemical facility, turning a large backlog of site redlines into revised CAD drawings and a complete Final Record Dossier for handover. The deadline was tied to the plant's re-start authorisation.
Problem / Requirement
Following the mechanical completion of a brownfield revamp at a petrochemical facility, the EPC contractor was required to close out a large backlog of redline mark-ups across piping, structural and equipment drawings, incorporate the changes into revised CAD files, and compile a Final Record Dossier (FRD) and Manufacturer's Data Report (MDR) package to satisfy the facility owner's handover requirements. The documentation scope covered over 120 drawing sheets across multiple disciplines, with a handover deadline tied to the plant's re-start authorisation.
Engineering Scope
Deliverables
Client Value Delivered
Standards Referenced
Software Used
Need Similar Engineering?
Contact SLETEC to discuss your project scope and receive a tailored proposal.
Request SupportMethod: review redlines before touching CAD
Redlines from several construction teams rarely agree with each other. Each mark-up was therefore reviewed against the IFC revision first and sorted into clear changes, changes needing clarification and conflicting changes.
Only clear changes went straight to CAD. Unclear and conflicting items were raised with the site team and resolved before incorporation, so errors were not locked into the permanent record.
Checks performed on every as-built sheet
Each revised sheet was checked against its redline before issue. The checks are simple, but missing any one of them is a common reason for an owner to reject a handover package.
- Every redline change incorporated, and nothing else altered
- Revision cloud, change description and revision block updated
- Cross-references between isometrics, P&IDs and GA drawings still consistent
- Sheet listed in the drawing register at the correct as-built revision
How the final record dossier was organised
The dossier was indexed to match the owner's document management system, so the handover could be filed without rework. The MDR was assembled per equipment tag, with mill certificates, weld maps, NDE, PWHT and hydrotest records cross-referenced, and the transmittal register gave proof of every handover. Our guide on how to prepare as-built drawings explains the redline incorporation steps in more detail.
Related engineering topics
brownfield engineering, as-built drawings, reverse engineering case study and how to prepare as-built drawings.
Frequently asked questions
- What is an as-built dossier?
- The final record of what was built — as-built drawings, calculations, material certificates, inspection records and transmittals — handed over at project close-out.
- Can SLETEC convert redline markups to as-built CAD?
- Yes, including revision registers and controlled transmittals.
Last updated: