Equipment Foundation Drawings – Civil Foundation & Installation Package
This package of equipment foundation drawings covered two vertical vessels, a horizontal pressure vessel, a pump skid and a fin fan cooler structure on a site with variable ground conditions. It had to satisfy the civil contractor's IFC needs and an owner's third-party review at the same time.
SLETEC portfolio
Project Images & Evidence — Structural, Civil, Platforms & Access Systems
Selected engineering evidence from SLETEC projects. Client names and identifiers are withheld for confidentiality.
Scope
Platforms, racks, supports, anchors, foundations, skids
Codes
AISC 360 · AWS D1.1 · ACI 318 · ASCE 7 · SBC
Deliverables
Structural calcs, steel & foundation drawings, MTO
Problem / Requirement
A greenfield industrial facility required civil foundation design for multiple items of heavy static equipment including two vertical vessels, one horizontal pressure vessel, a pump skid and a fin fan air cooler structure. The site geotechnical report indicated variable bearing capacity across the plot, with one vessel location requiring piled foundations. The engineering package had to satisfy the civil contractor's IFC requirements and the owner's third-party structural review in parallel.
Engineering Scope
Deliverables
Client Value Delivered
Standards Referenced
Software Used
Need Similar Engineering?
Contact SLETEC to discuss your project scope and receive a tailored proposal.
Request SupportDesign basis and load inputs
Foundation design starts from the equipment loads, so vendor data was collected for each item: empty, operating and test weights, wind and seismic reactions, and the anchor bolt pattern. These were combined with the allowable bearing pressures from the geotechnical report for each soil zone.
Loads followed ASCE 7 and concrete design followed ACI 318, with ACI 351.3R guidance for equipment foundations.
Checks performed on each footing
Every footing type was taken through the same set of checks before reinforcement was detailed.
- Bearing pressure against the allowable value for that soil zone
- Overturning, sliding and uplift under wind and seismic combinations
- Pedestal size and anchor edge distances
- Anchor bolt tension, shear and combined interaction
- Pile capacity and pile cap design where spread footings were not adequate
Lessons for foundation packages
Positioning pads within competent-ground zones limited piling to one equipment location. The installation sequence drawing, showing setting-out, grouting and bolt tensioning, proved as useful to the contractor as the reinforcement drawings themselves.
Related engineering topics
steel structure design, structural calculations, steel platform FEA and structural steel detailing.
Frequently asked questions
- What drawings were issued?
- Footing plan, pedestal reinforcement and section details for an equipment foundation, including anchor and construction notes.
- Which code is used for foundation design?
- ACI 318 for reinforced concrete, with loads to ASCE 7 or the Saudi Building Code.