Case Study

Equipment Foundation Drawings – Civil Foundation & Installation Package

This package of equipment foundation drawings covered two vertical vessels, a horizontal pressure vessel, a pump skid and a fin fan cooler structure on a site with variable ground conditions. It had to satisfy the civil contractor's IFC needs and an owner's third-party review at the same time.

Civil & Structural EngineeringConfidential Details Removed
Request Similar Engineering Support WhatsApp

SLETEC portfolio

Project Images & Evidence — Structural, Civil, Platforms & Access Systems

Selected engineering evidence from SLETEC projects. Client names and identifiers are withheld for confidentiality.

Foundation & Installation PackageAnchors, rail alignment, reinforcement, concrete details and construction notes.
CF8 Footing — Section K reinforcementPedestal reinforcement and section details.
Civil & Foundation drawingRepresentative civil and foundation drawing package.
CF8 Footing — Section L reinforcementPedestal reinforcement and section details.

Scope

Platforms, racks, supports, anchors, foundations, skids

Codes

AISC 360 · AWS D1.1 · ACI 318 · ASCE 7 · SBC

Deliverables

Structural calcs, steel & foundation drawings, MTO

Problem / Requirement

A greenfield industrial facility required civil foundation design for multiple items of heavy static equipment including two vertical vessels, one horizontal pressure vessel, a pump skid and a fin fan air cooler structure. The site geotechnical report indicated variable bearing capacity across the plot, with one vessel location requiring piled foundations. The engineering package had to satisfy the civil contractor's IFC requirements and the owner's third-party structural review in parallel.

Engineering Scope

Review of geotechnical report and determination of allowable bearing pressures per soil zone
Foundation type selection — spread footings versus piled foundations — based on equipment loads and soil capacity
Isolated pad footing design for equipment on competent ground: size, depth, reinforcement and concrete grade per ACI 318
Pile schedule design for the vertical vessel pad: pile capacity, pile cap geometry and reinforcement
Anchor bolt design (tension, shear and interaction) for all equipment types using ACI 318 Appendix D method
Grout pocket and bedplate detail design to transmit equipment loads into foundation concrete
Equipment installation sequence drawing showing setting-out, grouting and bolt tensioning stages
Preparation of civil specification clauses for anchor bolt installation, grout specification and inspection hold points

Deliverables

Foundation Design Calculation Report — Spread Footings Pile Foundation Design Calculation Report — Vertical Vessel Anchor Bolt Design Calculation Sheets (×5 equipment types) Foundation Layout Plan — Setting-Out Dimensions Foundation Detail Drawings — Pad Footing Reinforcement (×4 types) Pile Cap and Pile Schedule Drawing Equipment Installation Sequence Drawing Anchor Bolt and Grout Specification Document

Client Value Delivered

Full IFC foundation drawing package issued within five weeks, keeping pace with the overall civil construction programme
Pile foundation scope was limited to a single equipment location by optimising pad layout within competent-ground zones, reducing piling cost
Anchor bolt schedule in a standard procurement format enabled direct material ordering without further engineering input
Installation sequence drawing eliminated ambiguity for the construction contractor and removed a key hold point from the inspection plan
Third-party structural review passed with no major comments, reflecting the quality and completeness of the calculation package

Standards Referenced

ACI 318-19 ACI 351.3R (equipment foundations) ASCE 7-22 IBC 2021 API 686 (equipment installation) ASTM A193 Gr.B7 (anchor bolts) ASTM C109 (grout compressive strength)

Software Used

STAAD Foundation Advanced (Bentley) AutoCAD 2024 Microsoft Excel (anchor bolt and bearing pressure worksheets) HILTI PROFIS Anchor (anchor bolt verification) ETABS 2023 (pile cap model — secondary check)

Need Similar Engineering?

Contact SLETEC to discuss your project scope and receive a tailored proposal.

Request Support

Design basis and load inputs

Foundation design starts from the equipment loads, so vendor data was collected for each item: empty, operating and test weights, wind and seismic reactions, and the anchor bolt pattern. These were combined with the allowable bearing pressures from the geotechnical report for each soil zone.

Loads followed ASCE 7 and concrete design followed ACI 318, with ACI 351.3R guidance for equipment foundations.

Checks performed on each footing

Every footing type was taken through the same set of checks before reinforcement was detailed.

  • Bearing pressure against the allowable value for that soil zone
  • Overturning, sliding and uplift under wind and seismic combinations
  • Pedestal size and anchor edge distances
  • Anchor bolt tension, shear and combined interaction
  • Pile capacity and pile cap design where spread footings were not adequate

Lessons for foundation packages

Positioning pads within competent-ground zones limited piling to one equipment location. The installation sequence drawing, showing setting-out, grouting and bolt tensioning, proved as useful to the contractor as the reinforcement drawings themselves.

Frequently asked questions

What drawings were issued?
Footing plan, pedestal reinforcement and section details for an equipment foundation, including anchor and construction notes.
Which code is used for foundation design?
ACI 318 for reinforced concrete, with loads to ASCE 7 or the Saudi Building Code.

Last updated: